Exmouth to Lympstone
Bank remedial works completed
Vandalised Information boards to be replaced
Lympstone to Exton
Work on Nutwell Court to Exton almost complete. Section now available to the public as a “no through route”
Contract for Lympstone to Nutwell Court already awarded; work to commence early October; Completion anticipated early next Spring
Exton to Topsham
Land negotiations re access and works areas are ongoing
Advanced works at Goosemoor completed
Main construction works scheduled to start 2010 for two years
Bridge Road to Turf Lock
Main works complete
RSPB viewing facility to be erected this month
2m wide by-pass path at Turf Lock to be constructed this month
Turf Lock to Powderham Church
Conditional Planning Approval received
Design ongoing re Bridge Appearance
Negotiations with the three landowners re access and works areas are ongoing
Works currently scheduled to commence 2011
Powderham Church to Exeleigh Junction
New surface dressing of Estuary Road completed
“Shared Road” facility and 20mph signs to be erected this month
Exeleigh Junction to Starcross
Works complete
Starcross to Cockwood
Works complete
Cockwood to Dawlish Warren
Negotiations with the two landowners are ongoing
Funding for works likely in 2010